Report Disputes Christie’s Basis for Halting Tunnel

This article was published in the New York Times. It is quoted here as a matter of interest, and does not necessarily reflect the views of the Lackawanna Coalition.

Gov. Chris Christie of New Jersey exaggerated when he declared that unforeseen costs to the state were forcing him to cancel the new train tunnel planned to relieve congested routes across the Hudson River, according to a long-awaited report by independent Congressional investigators.

The report by the Government Accountability Office, to be released this week, found that while Mr. Christie said that state transportation officials had revised cost estimates for the tunnel to at least $11 billion and potentially more than $14 billion, the range of estimates had in fact remained unchanged in the two years before he announced in 2010 that he was shutting down the project.  And state transportation officials, the report says, had said the cost would be no more than $10 billion.


http://www.nytimes.com/2012/04/10/nyregion/report-disputes-christies-reason-for-halting-tunnel-project-in-2010.html?nl=todaysheadlines&emc=tha29_20120410 (limited access; paywall)